At the west building façade, a portion of foundation wall and entire terrace
were removed at the ground level and a window wall was removed on the main
level to connect and transition the existing building and the new. The north
and south basement walls were excavated with a minimum number of punched windows
added to maintain structural integrity while providing daylight to classroom
and offices now located in the lower level which was converted from storage space. Original brick veneer
was maintained and new brick was installed at the exposed foundation walls.
The original structure is concrete columns, beams, waffle and t-slabs. The
interior was gutted except for two wood paneled conference rooms and a marble
stair that connects three levels.
|